On average, it takes 60 to 90 days from your initial consultation before we submit your project for permit.
Here’s what happens during that time:
- Project scope & pricing: Your project consultant works with you to finalize details and pricing.
- Property research: We confirm that your project complies with all regulations.
- Renderings (if applicable): If you’ve purchased renderings, we’ll send you plans for review and approval before moving to technical drawings.
- Technical set: If you didn’t purchase renderings, we move straight into drafting the technical set of plans. These are also sent to you for QC and approval.
- Engineering & application: Once approved, plans go to engineering, and we prepare all documents needed for submission to the jurisdiction.
Your timely feedback is critical. Quick responses help keep the process smooth and shorten the timeline to permit submission.